Whilst noting that progress continues elsewhere with both our A1 and P2, the focus in Darlington must be on getting the track down in time for S&D 200 next year and, thanks to our supporters' generous donations to the ballast fund, great...
4341
Now that the dust has settled after the election, and rules around purdah lifted, we can tell you all about the hive of activity at DLW at the start of June! In the first weekend in June, 507 STRE (Railway Infrastructure) Royal Engineers...
19 October 2021
Prince of Wales, Our Latest News
The tender frames continue to make progress at I.D.Howitt’s works at Crofton, Wakefield. As the accompanying photos show, the adjustable brake pull-rods and tie bars between the lower ends of the...
07 October 2021
P2 progress on all fronts as pony truck and coupling rods trial fitted for the first time The project to build new Gresley class P2 steam locomotive No. 2007 Prince of Wales is delighted to...
01 October 2021
Mikado Messenger
14 September 2021
Cylinders and valves - Having gone through a thorough selection process, the order for the fabricated cylinder block was placed with Howco at Irvine in Scotland. Howco is part of a large Japanese...
10 September 2021
Pony Truck - The pony truck main frame has been returned from the manufacturer following final machining. The side control spring components are having the final machining processes completed at...
20 August 2021
Fundraising to date: Our ‘P2 for the price of a pint of beer a week’ Covenant scheme has attracted over 1,000 Covenantors to-date - now is the time to come on-board or recruit a friend! ...