Whilst noting that progress continues elsewhere with both our A1 and P2, the focus in Darlington must be on getting the track down in time for S&D 200 next year and, thanks to our supporters' generous donations to the ballast fund, great...
4341
Now that the dust has settled after the election, and rules around purdah lifted, we can tell you all about the hive of activity at DLW at the start of June! In the first weekend in June, 507 STRE (Railway Infrastructure) Royal Engineers...
05 December 2019
Prince of Wales, Our Latest News
The pre-fitting of the tender tank baseplate to the tender frames was completed at Ian Howitt’s works at Crofton near Wakefield where a total of 96 blind nuts were welded to the baseplate. The...
01 December 2019
Mikado Messenger
04 November 2019
South Devon Railway Engineering has delivered the tender wheelsets which will now have cartridge roller bearings fitted and then be sent for balancing (photos SDR(E) and A1SLT).
03 November 2019
South Devon Railway Engineering has delivered the tender wheelsets which will now have cartridge roller bearings fitted and then be sent for balancing.
25 October 2019
22 October 2019
The A1 Steam Locomotive Trust has announced that it has received pledges for more than two-thirds of the £5m required to complete new Gresley class P2 No. 2007 Prince of Wales. The Trust also...