Introducing 21st Century Steam...

25 May 2022

Our Latest News

The A1 Steam Locomotive Trust is delighted to introduce the new name for its railtours business: 21st Century Steam Ltd.

Overhaul over-run explained

13 May 2022

Our Latest News

Tornado’s overhaul programme is running slightly later than expected. This is focussed in three main areas. The boiler will be back around the end of May, rather than the beginning....

Early May overhaul news –...

08 May 2022

Our Latest News

Tornado’s atomisers are in the process of been overhauled at Darlington Locomotive Works (DLW). This is a very small and fiddly but necessary time-consuming job.  The atomisers are...

Early May overhaul news –...

08 May 2022

Our Latest News

In Loughborough, at Locomotive Maintenance Services, work is continuing to ready Tornado for receipt of the larger components being overhauled in various locations, such as the boiler...

Forging, not cutting, corners!

19 April 2022

Our Latest News

Steam locomotives are always a challenge in boiler design, and the larger the power output the bigger the challenge. The restrictions of maximum axle load and of the loading gauge (clearance with...

Tender Wheelset Overhaul

08 April 2022

Our Latest News

Tornado‘s tender wheelsets were sent to South Devon Railway (Engineering) for retyring. The work is making good progress, as can be seen in the images below. They will be back at...