31 December 2007
Tornado, Our Latest News
Thanks to the generosity of our many supporters work has been able to be continued at a fast pace in Darlington Locomotive Works. As the momentous day of the steam test draws nearer the...
20 December 2007
The funding gap needed to be bridged to complete Tornado has shrunk from £55,052 to £49,434 over the past month. Mark Allatt, chairman of The A1 Steam Locomotive Trust commented: "With less...
17 December 2007
As part of the Trust’s preparation for Tornado’s steam test in early January the first phase of track laying at Darlington Locomotive Works has now been completed. Here we have the first...
07 December 2007
Yesterday, Thursday 6th December marked another significant milestone in the progress towards completion - the tender frames arrived in Darlington from builder Ian Howitt Ltd. using a mobile...
06 December 2007
On Monday 3rd the BBC's "Working Lunch" programme ran a very good feature on the work of The Trust; this can be viewed at:http://news.bbc.co.uk/1/hi/programmes/working_lunch/7124643.stm