Skip to main content

Autumn 2024

12 December 2024

The Communication Cord, The Communication Cord, The Communication Cord

Autumn tracklaying update

08 December 2024

Our Latest News, Our Latest News

Whilst noting that progress continues elsewhere with both our A1 and P2, the focus in Darlington must be on getting the track down in time for S&D 200 next year and, thanks to our...

November ETCS update

14 November 2024

Our Latest News

We carried out tests providing power to the ETCS from our existing two locomotive power supplies.  We could do this in the event of a complete failure of the ETCS battery and...

October ETCS update

18 October 2024

Our Latest News

With the engine’s arrival at the Great Central Railway (GCR) it was possible to couple the engine and tender together for the first time following the overhaul.  This allowed us to...

Tornado Main Line Return Delayed

09 September 2024

Our Latest News

The Trust has made the very difficult decision to cancel ‘The Ribblehead Rambler’ on Saturday 21st September. We apologise wholeheartedly to all those who have been looking...

August 2024

22 August 2024

The Tornado Telegraph

12345